Quantcast

Kalamazoo Times

Sunday, May 19, 2024

M-15 / Clark Street Road Project

Road

** Schedule subject to change**

Project Starts on or about April 18th. 

 Stage I and II will have single lane closures on Northbound and Southbound M-15 to work at Lexington Street/Birch Drive and South Street and prepare those intersection with temporary signals and pedestrian crossings.

 Lexington/Birch and South Street would be open but at times may need to intermittently close for some of the work.  

 Stage III would start on June 20th and would close SB M-15 (detour west on Flint Street/Davison Road to Irish Road south to Eastbound I-69 back to M-15).

 During Stage III we would work on the west side of M-15, this would close Lexington.

 Once Lexington is complete Stage IV would start and close the west side of Clark.  This would also close access from the east side of Clark Street to M-15 keeping access open to Vogts Flower Shop, from Main Street.  Pedestrian access along M-15 will be maintained on the east side of the road and across Clark Street on the east side of M-15.

 Stage V would start once the west side of M-15 and Clark Street are done we would have 1 lane open for northbound and southbound with traffic on the west side of M-15. Work would start on the east side of M-15 and close Clark Street from M-15 east to the drive by Vogts.  

 Stage V would have Clark Street open by about August 6th and M-15 open by August 25th with just cleanup and restoration after this. 

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS